JoyOne factory · fence takeoff

Fence Post Concrete Calculator: Bags per Hole, by Bag Size

Hole, post, gravel, bag. The calculator subtracts the post from the hole, takes the gravel off the bottom, and tells you bags per hole and bags for the whole fence.

Bags per holeEvery bag sizeGravel deductedSection drawing

204 bags

6 per hole · 1.9 cu ft each

The holes
posts
in
in
in
The post and the bag

Loose or sandy soil gets 20% more concrete for the dish-shaped hole.

Every field is a starting point: change it and the takeoff follows. Numbers stay in your browser and a shared link keeps them after the #, which is never sent to a server.

Takeoff

6 bags per hole

204 bags for 34 posts · 1.9 cu ft per hole

Concrete per hole
1.9 cu ft32.5 in pour
Bags per hole
650 lb fast-setting
Bags total
20434 holes
Pour volume
2.13 cu ft12 in hole, 42 in deep
Post displaces
0.23 cu fttaken off the hole
Gravel
0.39 cu ft6 in base, no concrete
Soil cap
3.5 inbackfilled above the pour
Section through one post: 1' 0" above grade, 3' 6" hole with 6 in of gravel, post 3.5 in wide in a 12 in hole. above 1' 0"buried 3' 0"3.5 in soil6 in gravel

Same hole, every bag on the shelf

BagPer holeTotalConcrete orderedSelected
50 lb fast-setting62042.25 cu ftyours
60 lb fast-setting51702.25 cu ft
40 lb standard72382.1 cu ft
50 lb standard62042.25 cu ft
60 lb standard51702.25 cu ft
80 lb standard41362.4 cu ft
90 lb standard31022.03 cu ft

Yields are the manufacturers’ published figures: QUIKRETE 1004 fast-setting and 1101 Concrete Mix, SAKRETE high-strength. A bag is sold by weight and yields by volume, so the same hole is four bags or eight depending on the label.

Posts for this fence

ItemValueWhy
Buried depth3' 0"deeper of the two manufacturer rules
Hole depth3' 6"buried + 6 in gravel base
Post to buy10 ftstandard stock: 8, 10, 12 ft
Cut off1' 0"treat the cut end before it goes in the ground

Concrete is the hole minus the post minus the gravel. Round up: a hole that is an inch wide costs a whole extra bag across a fence.

Worked examples

Every number below comes from the same engine that runs in the browser, at build time, so the examples cannot drift from the calculator above.

Hole and postConcrete50 lb fast-setting80 lb standard
9 in × 30 in, 3x3 post0.65 cu ft22
12 in × 36 in, 4x4 post1.55 cu ft54
12 in × 42 in, 4x4 post1.9 cu ft65
12 in × 48 in, 6x6 post1.85 cu ft55

The first row is the manufacturer’s own worked example: two 50 lb bags for a 3 in post in a 9 in hole 30 in deep. The engine returns 1.73 bags before rounding, and two after it.

Concrete is what is left in the hole

The volume of concrete a post takes is the hole minus the post minus the gravel. That sounds obvious and it is where most estimates go wrong, because the post is bigger than its nominal size suggests and the gravel is a real layer, not a rounding. A 4x4 is 3 1/2 in square in the ground; over 32 1/2 in of pour it displaces 0.23 cu ft, which is most of a 50 lb bag that a hole-only calculation would order twice.

The hole itself is a cylinder, and the radius is half the diameter — a mistake that doubles the answer when it is made the other way round. A 12 in hole 42 in deep, with 6 in of gravel at the bottom and 3 1/2 in of soil left on top, is a 32 1/2 in pour: π × 0.5² × 2.7083 = 2.13 cu ft. Take the post out (0.23) and 1.90 cu ft is left, which is six 50 lb bags at 0.375 cu ft each. That is the number on this page for the default fence, times 34 posts: 204 bags.

The depth that counts for concrete is not the hole depth. It is the hole depth minus the gravel base and minus the 3 to 4 in the fast-setting instructions leave for soil, because the post sits on the stone and the concrete stops below grade. The calculator takes both off first, then subtracts the post, then divides by the bag’s yield — in that order, because each step changes what the next one is measuring.

A bag is a label, not a constant

Bagged concrete is sold by weight and yields by volume, and the ratio is not the same across products. QUIKRETE’s fast-setting mix yields 0.375 cu ft from 50 lb and 0.45 cu ft from 60 lb; their standard Concrete Mix yields 0.30, 0.375, 0.45, 0.60 and 0.675 cu ft from 40, 50, 60, 80 and 90 lb bags. SAKRETE’s high-strength mix is 0.30, 0.45 and 0.6 cu ft at 40, 60 and 80 lb. The same hole can be four bags or seven depending on which bag you carry.

That is why the comparison table matters more than the single answer. On the default hole, 80 lb standard bags give four per hole and 204 becomes 136; 40 lb bags give seven and 204 becomes 238. The weight of concrete is identical — what changes is the number of bags you lift, the number of cuts you make in the pallet wrap and the price per cubic foot the yard charges.

Fast-setting and standard mix are not interchangeable in use even though the arithmetic is the same. Fast-setting reaches its initial set in 20 to 40 minutes, which is what lets you pour dry, add water and walk away; standard mix wants mixing in a barrow and 24 hours before you lean on it. For a fence post, the fast-setting dry-pour method is the reason most people can set 34 posts in a weekend at all.

Bags for the default 12 in × 42 in hole, 4x4 post, 6 in gravel

Gravel, water and the three inches you leave at the top

The gravel base is 6 in of crushed stone or all-purpose gravel at the bottom of the hole, and it does two jobs: it drains, and it gives the post something flat to stand on so the concrete does not have to carry the post’s full weight while it sets. The manufacturers’ setting instructions both call for it, and the calculator subtracts it from the concrete rather than ignoring it, because 6 in of a 42 in hole is a sixth of the hole’s depth and comes off the pour before a bag is counted.

The fast-setting method is a dry pour: stand the post on the gravel, pour the mix dry from the bag until it is 3 to 4 in below grade, check the post for plumb, then pour water on top and let it soak through. QUIKRETE suggests about a gallon of water per 50 lb bag. That 3 to 4 in of headspace is then backfilled with soil, which is why the concrete volume here is computed to the top of the hole and the bags are rounded up: the extra is the margin for a hole that is not perfectly cylindrical.

In sandy or loose soil both manufacturers say to dig a wider, dish-shaped hole so the concrete collar, not the soil, resists the load. The calculator adds 20% to the concrete volume for that and labels it, rather than pretending a neat cylinder is what you dug.

The two-bag check that keeps the arithmetic honest

QUIKRETE’s fast-setting data sheet contains a worked example that is worth more than any formula: two 50 lb bags will set a 3 in square post in a 9 in diameter hole 30 in deep. Run that through the same arithmetic and the pour is 30 − 6 − 3.5 = 20.5 in deep: 0.754 cu ft of hole, less 0.107 cu ft of post, leaving 0.647 cu ft, which is 1.73 bags. The manufacturer says two bags, the engine rounds 1.73 up to two, and that agreement is a test in this site’s suite.

The check also shows why the gravel and the soil cap matter. Fill the same hole to the top, with no gravel and no gap, and it asks for 2.53 bags, which rounds to three and sends you back to the store for a bag you do not need. The layers are not a detail; they are three quarters of a bag per hole on a small post and dozens of bags over a long fence.

If your answer is far from any published example, the cause is almost always the hole diameter. A 10 in hole instead of 12 in takes 30% less concrete, and a 14 in hole takes 36% more. Measure the auger, not the post.

Ordering, mixing and the bags you will actually carry

Order the bag count rounded up and add one per ten posts. A hole that is an inch wider than planned, a root that pushes the auger sideways, or clay that slumps into the hole all take more concrete, and a half-set post with no concrete is worse than a spare bag on the pallet. On 34 posts that is three extra bags, which is cheap insurance.

Mixing has its own arithmetic. A 50 lb bag of standard mix takes about 2.5 to 3 quarts of water in a barrow and makes roughly 0.375 cu ft, which is a 12 in hole about 6 in deep. Six bags is six barrows per post, which is why the dry-pour method exists: no barrow, no hose in the mix, and the water goes in after the mix is already in the hole.

Finally, weight. 204 bags of 50 lb mix is 10,200 lb, which is more than a half-ton pickup should carry in one trip and more than a pallet plus a helper will move in an afternoon. Check the load rating before you hook up the trailer, and check whether the yard delivers for less than the fuel.

Questions people ask before digging

How many bags of concrete do I need per fence post?

For a 4x4 post in a 12 in hole with 6 in of gravel and 3 1/2 in left for soil, about six 50 lb bags of fast-setting mix, or four 80 lb bags of standard mix. The pour is 32 1/2 in deep and holds 2.13 cu ft; the post takes 0.23 cu ft of that, leaving 1.90 cu ft of concrete.

Should I put gravel in the bottom of a post hole?

Yes. Six inches of crushed stone or all-purpose gravel gives the post a flat, drained base and keeps the end grain out of standing water. Both major manufacturers’ installation sheets call for it, and it removes about 16% of the concrete a hole would otherwise need.

Can I pour concrete dry and add water afterwards?

That is the fast-setting method: pour the dry mix into the hole around a plumb post, stop 3 to 4 in below grade, then pour water on top and let it soak through, about a gallon per 50 lb bag. It works with fast-setting mix, which sets in 20 to 40 minutes. Standard mix wants mixing in a barrow first.

How big should the hole be for a 4x4 post?

About 12 in across, which is three times the nominal 4 in, or 3.4 times the actual 3 1/2 in. Both QUIKRETE and SAKRETE give the three-times rule, and SAKRETE’s example is explicit: a 4 in post needs a 12 in hole.

Why does a 9 inch hole only take two bags when my 12 inch hole takes six?

Volume goes with the square of the diameter. A 9 in hole is 44% of the cross-section of a 12 in hole, so at similar depths it takes less than half the concrete. The 9 in figure is from the manufacturer’s own example: two 50 lb bags for a 3 in post in a 9 in hole 30 in deep.

Every number on this site, with where it came from

ValueAs used hereBasisSource
Post hole diameter3x the post“The diameter of the posthole should be 3 times the post diameter.” SAKRETE gives the same rule with a worked example: “a 4 in post will require a 12 in hole”.QUIKRETE, “Setting Posts” project sheet
Post hole depth (manufacturer rule)1/3 of overall post + 6 in gravel“Hole depth should be 1/3 the overall post length, plus 6 in (150 mm) for the gravel base.” SAKRETE’s version is one third of the height above ground. This site takes the deeper of the two.QUIKRETE, “Setting Posts” project sheet
Frost lineat least 6 in below it“When the post is to be used for structural support … the hole must extend at least 6 in (150 mm) below the frost line.” The local frost depth itself is set by the building department, not by this page.QUIKRETE, “Setting Posts” project sheet
Gravel base under a post6 in“place 6 in (150 mm) of … gravel or crushed stone in the hole to aid in drainage.”QUIKRETE, “Setting Posts” project sheet
Bag yield, fast-setting0.375 cu ft (50 lb), 0.45 cu ft (60 lb)Data sheet yield table. SAKRETE’s high-strength mix yields 0.30 / 0.45 / 0.6 cu ft at 40 / 60 / 80 lb, so a “bag” is never a fixed volume.QUIKRETE Fast-Setting Concrete Mix, data sheet 1004
Bag yield, standard mix0.30 / 0.375 / 0.45 / 0.60 / 0.675 cu ftYield table for 40, 50, 60, 80 and 90 lb bags.QUIKRETE Concrete Mix, data sheet 1101
Bag count, worked example2 x 50 lb bags“Two 50 lb bags … will set a 3 in square post in a 9 in diameter hole 30 in deep.” The engine reproduces that count from the hole and post volumes, with the 6 in gravel base included.QUIKRETE Fast-Setting Concrete Mix, data sheet 1004
Post spacing convention6, 8 or 10 ft equal intervals“Divide this length into equal intervals of 6 ft, 8 ft, or 10 ft … In this way standard precut lumber can be used for the crossrails.” 8 ft is the default here because 8 ft is the rail length sold everywhere.QUIKRETE, “Fence and Trellis Designs” project sheet
Rail count convention2 rails to 6 ft, 3 aboveConvention, not code. The manufacturer’s fence design uses a top rail plus bottom and middle rails, i.e. three; two rails on a 4–6 ft fence is the common trade practice this site starts from.QUIKRETE, “Fence and Trellis Designs” project sheet
Stain coverage250–600 ft²/gal, one coatProduct details state coverage of 250 ft²/gal to 600 ft²/gal with one coat recommended. The default here is the low end, 250 ft²/gal, and every field is editable.Cabot Australian Timber Oil
Dressed lumber sizes4x4 = 3.5 in, 6x6 = 5.5 in, 1x6 = 5.5 inPS 20 surfaced sizes, read from the standard: nominal thickness and width are reduced by planing. The engine keeps them in one table and a test asserts each value.ALSC, American Softwood Lumber Standard PS 20
Feet to metres1 ft = 0.3048 m exactlyThe international foot is defined as exactly 0.3048 m; the metric column is a conversion, not a second measurement.NIST SP 811, Guide for the Use of the SI

Sources

These are quantity estimates. Post depth and frost depth are set by your local building department, hole and footing sizes by your soil and your inspector, and panel and stain coverage by the product you actually bought. Check the manufacturer’s label and your local code before you dig, and call 811 (in the US) or your local utility locator before the first hole. Nothing you type leaves your browser.